Kano railway project advances as ministry weighs three-month test run
A pre-commissioning inspection found earlier safety concerns had been addressed, while a proposed test period still requires presidential approval.

Kano’s railway project has made progress towards commissioning, but regular services on the Jaji-Kano section may follow a proposed three-month test run that still needs presidential approval. Federal Ministry of Transportation Permanent Secretary Engr. Olufunso Adebiyi said the trial period would assess the railway’s structural integrity and operational performance before services begin.
Adebiyi made the remarks during a pre-commissioning inspection and train ride on Thursday. He commended the contractors for progress, including a successful trial journey from Jaji through Zaria to Kano, and said concerns raised during an earlier inspection had been addressed.
The project matters to Kano residents not only as a passenger and cargo link. Kano community representative Hamza Mohammed said residents were already gaining employment and security-related work, while commercial activity and young people’s businesses had increased around the project.
Safety, access and staff training
Adebiyi said toughened glass in areas accessible to passengers had been replaced with laminated glass, and lighting systems had been changed so installed bulbs would have a minimum service life of three years. Manlifts had also been provided for maintenance, and about four lifts were procured for people with disabilities, with further accessibility features being incorporated into the station design.
The Nigerian Railway Corporation has been asked to nominate engineers for specialist training, which will include classroom sessions and examinations. Adebiyi said only personnel who pass the training and exams would be retained for operational responsibilities at the stations.
Connection to Kaduna still has work outstanding
The remaining Kaduna-Kano section is estimated at 10 to 15 kilometres and includes a bridge and other outstanding work. Adebiyi said he was optimistic it would be completed within four to six months. The railway corridor has six stations: three major stations and three sub-stations.
Contractor representative Mark Xu said the Kano station was expected to be ready for the planned December commissioning. The inspection account did not state a specific commissioning date, and the proposed test-running period remains subject to presidential approval.
This report draws on information from Blueprint Newspapers Limited.
Editorial checks passed Facts, figures and quotes checked against 1 source